Complete Plants


It’s more than 20 years that Tecno-Beton. Impianti¬† designs, build and install aggregate processing plants.
Thanks to our cooperations with great world players, we are able to supply devices, plants and servicies that can support customers in every needing in quarry:

  • Underwater quarrying (clamshell or suction dredges);
  • Material handling (fixed, floating and special conveyor belts);
  • Crushing (Fron the big primary jaws to the final quaternary VSI and hammermills, passing through cone crushers);
  • Material separation and selection (from Big Heavy duty scalping sreens to final fines selection, using horizontal, inclined or Hi frequency screens);
  • sand washing and collecting;
  • Silt and mus thickeners adn waste waters processing systems.

All of this components added to our steelworks factory and electrical management, make Tecno-Beton. able to supply a complete “turnkey” plant.
The most important phases of a plant construction are:

  1. Parameters definition, working with customer’s technicians: feed gradation, products desired gradation, washing, flowsheets and so on…
  2. Flowsheet and produztion symulation, using AggFlow, the most complete and standard symulation software available today. this allow us to predict the major part of the plant behaviour ant to prevent possible errors (“in advance”).
  3. Plant Pre-Engineering. this is the first phase of the “real work”: we design a first layout that allow us to define tha space usage of the plant, the logistics questions and the maintenance issues. in this phase customer is completely involved in the decision process to let him to consider every part of this plant (this is a real “usage” project).
  4. Economical offer and deal.
  5. After a positive deal we start a “detailing ” phase that guides us to send final drawings to the steelwork facility (internal in Tecno-Beton.).
  6. Steelwork and devices manifacturing.
  7. delivery and assembly of the plant onsite.
  8. Test and validation of results.